Skip to main content
Skip table of contents

C.5 Project Results

The applicant can add Project Results to a list in this section.

  • Besides text input fields, a Programme Result Indicator has to be selected for each Result.

  • Once the Programme Result Indicator is chosen by the applicant, the measurement unit and baseline are automatically filled in.

  • The project baseline value is defined and prefilled by the programme result indicator baseline. The applicant can only lower this baseline up to 0,00 (e.g. in case of a smaller coverage area at project level vs the entire programme area).

For many common result indicators, the programme baselines are defined as 0,00. This means that the project baseline is automatically completed with 0,00 and that the applicant cannot change the baseline value for their project.

  • The Target value is by default 1,00 and can be increased by the applicant if multiple of the same Result are delivered.

The applicant can only choose Programme Result Indicators linked to the Programme Specific Objective selected in A- Project Identification.

This section can only be completed, if in section A- Project Identification the following fields are completed:

  1. The project duration (to be able to select delivery period)

  2. The specific objective (to be able to select indicators)

The numbering of results is a running number.

A maximum of 20 Project results can be added to one project.